Project Description

The Northern Access Link Expressway (“NALEX”) is Component 1 of Greater Capital Region Integrated Expressways Network. It consists of two (2) Phases. NALEX, Phase 1 is a proposed 136.4-kilometer expressway that is envisioned to provide connectivity between the Metro/Mega Manila, the New Manila International Airport (“NMIA”) and Central Luzon as an extension and/or linkage of the Metro Manila Skyway-Stage 3 (“MMSS3”) at Balintawak. NALEX, Phase 2 is a demand-driven expansion from Masantol, Pampanga to Tarlac City.

Supplemental Toll Operation Agreement (STOA) Approval

Approved  by the President of the Philippines on 06 May 2022.

Contracting Parties

Project Grantor: Toll Regulatory Board
Project Investor: SMC Northern Access Link Expressway Corporation
Project Operator: Skyway O&M Corporation

Concession Period

30 years from the issuance of the Toll Operation Certificate (TOC).

Project Cost

Php 148.30 Billion [October 2021 prices] (Phase 1).

Project Status

As of 10 March 2023:

  • On-going preparation of the Detailed Engineering Design (DED);
  • On-going Environmental Compliance Certificate (ECC) application with DENR for Phase 1 Section 1 (Balintawak - Obando);
  • DENR issued on 14 December 2022 the ECC fro Phase 1, Section 2 (Tulyahan to New Manila International Airport [NMIA]); and
  • On-going procurement of the Independent Consultant.

NALEX Project's Basic Alignment