Project Description

The Project is a 19.37 kms. six (6)-lane, all elevated expressway which will traverse the Pasig River from Radial Road 10 in the City of Manila to its termination at a connection with the proposed South East Metro Manila Expressway at Circumferential Road 6.  The Project will connect and utilize a 2.7-km. portion of Skyway Stage 3 from Nagtahan to Plaza Azul.

It consists of 3 Segments:

Segment 1

R-10 to Plaza Azul, 5.74 kms

5.74 kms

Plaza Azul to San Juan River (MMSS3)

2.70 kms

Segment 2 San Juan River to C5 Intersection 7.325 kms
Segment 3 C5 Intersection to C6 Intersection 6.30 kms

Supplemental Toll Operation Agreement (STOA) Approval

Approved  by the President of the Philippines on 14 March 2022.

Contracting Parties

Project Grantor: Toll Regulatory Board
Project Investor: Pasig River Expressway Corporation
Project Operator: Skyway O&M Corporation

Concession Period

30 years from the issuance of the Toll Operation Certificate (TOC).

Project Cost

Php 81.53 Billion [December 2020 prices]

Project Status

AS of 10 March 2023:

  • On-going preparation of the Detailed Engineering Design (DED);
  • On-going procurement of the Independent Consultant; and
  • On-going Environment Compliance Certificate (ECC) application with DENR.

PAREX Project Basic Alignment